Our most recent rail demolition project was a great success

We were appointed by Volker Fitzpatrick to complete a project for them during a 75 hour possession over the August bank Holiday.  The project was a brick arch spanning Long John Hill, Norwich. You were unable to pass under the bridge for some time as the bridge had been deemed structural unsound for vehicles to pass under. In order to keep the trains running above, the archway had to be filled with a large propping detail.

Volker Fitzpatrick had been on site for several months leading up to Bank Holiday as they were constructing a new concrete bridge, just a few metres away from where the crumbling one sat.

We started the first shift at 08:00 with small excavators moving onto the top of the bridge to start digging the soil from against the abutments. This soil was stockpiled on site so that it could be used once the new bridge was installed. The team started demolishing the bridge with 20t excavators with munching attachments working from the street, on either side of the bridge.  The 2 machines munched through the brickwork of the arch, progressively pulling out the props as they went. They met in the middle of the bridge just over 1 hour later. All of the masonry arisings were cleared from site for recycling at a local waste facility.

The night shift then started which involved trimming up the edges by hand down to the required finish line.  The new concrete bridge was then gradually manoeuvred into its new position. The voids around the bridge were then backfilled and compacted before the finally having the tracks and overhead cables being reinstated.

The project was completed without issue and well within the programme. We would like to congratulate the project team that planned and completed the project without any issues.

"On behalf of ARC, I would like to thank you (Downwell) for the service you provided over the 75hr possession at Long John Hill.

The works undertaken by you and your operatives enabled to works to be undertaken without any accidents and ahead of programme. We could not have done this without your involvement in the planning and safely executing the works."

Mark Taylor - Contracts manager for Volker Fitzpatrick.

100 years of demolition experience

Contact

Please select the division you wish to connect with:

Coronavirus (COVID-19) Statement - Wednesday 25th March

The Prime Minister’s announcement on Monday evening signalled the introduction of more stringent restrictions on us all and has specifically indicated that members of the public should only leave their home for very limited purposes. The message indicates that we should travel to and from work, only where this is absolutely necessary.

The management of the Downwell Group of companies which includes: Downwell Demolition, Inner City Environmental and Inner City Scaffolding has very carefully considered both the meaning and the spirit of the Prime Minister’s statement and whilst there has been some clarification from government subsequently that building sites could continue to operate, we came to the very clear decision yesterday that it was necessary for us, as a responsible contractor, to safely and securely close down our operational sites as soon as reasonably possible. Doing so will assist in maintaining the wellbeing of our customers, employees, sub-contractors, suppliers and the wider communities within which we build.

All sites have been closed down in a safe and secure manner and will remain closed until further notice.

We would like to take this opportunity of thanking all the key workers on the frontline who are continiung working for the good of us all.