New Covent Garden Enabling Works

A major enabling works project including asbestos removal, demolition and slab removal at New Covent Garden for Vinci Construction. The project value was £2.8 million.

Enabling works at New Covent Garden

A large enabling works project for at New Covent Garden for Vinci construction. The works involved carrying out various elements of asbestos works within the market to offices and units, demolition of the old Irish dock, partial demolition of a cantilevered canopy and removal of several high mast lighting towers to clear the way for the main works.

Additionally, we carried out a 23,000m2 ground stabilization and road formation project.

An Antigo breaker was used to break the vast slab area ready for lifting and processing then completed a bulk dig to over 5m in places. All materials had to be screened, which resulted in 85,000 m3 of arisings going through the screener,  plus around 12,000 – 15,000m3 of concrete went through the crushers.

The works included:

• Full obstruction removal and replacement of the materials to allow CMC piling to commence.

• Chemical testing to achieve the requirements under the material management plan. This was a requirement out as part of the planning consent.

• Relaying the ground back in place to perform ground bearing to check for suitability to become permanent work.

A large portion of the site was designated a medium risk UXO area, which had to be subject to careful excavation. The subsequent clearance to maximum bomb penetration depth meant the project was very challenging with a wide array of multi-layered activities undertaken at any one time.

Our original contract was digging to 2m, but a considerable quantity of large underground obstructions was below the 2m and removed to our works programme.

Downwell deployed up to 25 items of plant including excavators, screeners, crushers, rollers and dumpers working in tandem to achieve this project.

85,000 m3 of arisings going through the screener,  plus around 12,000 – 15,000m3 of concrete went through the crushers.

100 years of demolition experience

Contact

Please select the division you wish to connect with:

Coronavirus (COVID-19) Statement - Wednesday 25th March

The Prime Minister’s announcement on Monday evening signalled the introduction of more stringent restrictions on us all and has specifically indicated that members of the public should only leave their home for very limited purposes. The message indicates that we should travel to and from work, only where this is absolutely necessary.

The management of the Downwell Group of companies which includes: Downwell Demolition, Inner City Environmental and Inner City Scaffolding has very carefully considered both the meaning and the spirit of the Prime Minister’s statement and whilst there has been some clarification from government subsequently that building sites could continue to operate, we came to the very clear decision yesterday that it was necessary for us, as a responsible contractor, to safely and securely close down our operational sites as soon as reasonably possible. Doing so will assist in maintaining the wellbeing of our customers, employees, sub-contractors, suppliers and the wider communities within which we build.

All sites have been closed down in a safe and secure manner and will remain closed until further notice.

We would like to take this opportunity of thanking all the key workers on the frontline who are continiung working for the good of us all.